Case Study: Fire safety works at sheltered housing accommodation

Client: London Borough of Ealing

Value: £160,000

Form of Contract: Bespoke framework

Duration: 4 Weeks


Works included the replacement of flat front entrance doors for certified fire door sets, communal compartmentation doors, riser cupboard and electrical intake cupboard doors.


Large fire rated glazed screens were also installed in addition to comprehensive firestopping of service

penetrations within risers, ceiling voids and the boiler room.


New compliant fire safety signage was installed throughout.


All work was undertaken in occupation and completed and successfully handed over within 4 weeks.


Click here to download PDF of case study.